On Wednesday, 9/6/23, Depew Ave is scheduled for a road resurfacing project by Gorman Industries. The project will start at the gate of Memorial Park and finish west at S. Franklin Street. Thank you for your patience and cooperation with the paving projects!
July 5, 2023
Lydecker Street is completed as of 10:30am on 7/5/2023 - it's cooling off now!
Gedney Street is in the process of being paved as of 11:00 am - please observe all road closures!!
Upper Main Street & Pine Street will be paved on Thursday, July 6, 2023
All cars off the road by 6am on paving days! Roads will remain blocked to all traffic for hours after the paving until the roadway has cooled to driveable surface.
Village Marina Lot and Artopee Lot are available at no charge to residents during paving. North Broadway will have overnight parking restrictions lifted so that cars can be moved in advance of the road work. Midland Ave (between High Ave and Depew Ave) will also have overnight parking restrictions lifted during road construction.
Nyack Middle School is available for residents of Upper Main Street and Pine Street during paving.
Please plan accordingly if you need access to your vehicle on paving days.
ALL CARS OFF THE ROADS & OUT OF DRIVEWAYS BY 6AM ON MILLING & PAVING DAYS.
WHERE TO PARK ?? CLICK HERE!!
Any questions? Please call Mr. Jonathan Abrams at 845-401-3228
June 28, 2023 2pm: All road milling is complete, roads have been reopened and residents may park along Pine Street. THERE IS NO PAVING PLANNED FOR 6/30 OR 7/3. CHECK BACK FOR PAVING SCHEDULE.
June 28, 2023 9am: Milling on Upper Main Street has finished and construction has moved to Pine Street. Main Street is expected to reopen to vehicular traffic within the hour. THE VILLAGE IS WAITING FOR TILCON TO CONFIRM PAVING DATES - CHECK BACK FREQUENTLY - AS SOON AS WE KNOW THE WEBSITE WILL BE UPDATED. THERE WILL BE NO PAVING ON FRIDAY 6/30/23 OR MONDAY 7/3/23. PAVING IS LIKELY LATER NEXT WEEK - BUT NO DATES HAVE BEEN CONFIRMED YET !!
June 27, 2023 6pm: Milling of Lydecker and Gedney Streets is 100% complete. Drive carefully!! Milling has begun at the intersection of Main St and Midland Ave. Tomorrow, June 28, 2023 Tilcon will return to finish the milling work on Main Street and Pine Street. Residents of Main St and Pine Street - all cars off the roads tomorrow please!
THE PAVING SCHEDULE HAS NOT BEEN FINALIZED - WE WILL UPDATE ASAP - CHECK BACK FREQUENTLY.
ALL CARS OFF THE ROADS & OUT OF DRIVEWAYS BY 7AM ON MILLING & PAVING DAYS.
WHERE TO PARK ?? CLICK HERE!!
UPDATE!! June 27, 2023 at 11am:
Lydecker road milling is completed. Gedney Street is expected to finish within the next two hours. All roads in this area will be completely reopened when the milling work is complete - please drive SLOWLY over milled roads!! The crews are planning to move to Upper Main Street if the weather cooperates. In the event of heavy rain or downpours, this will delay the work on Upper Main Street until tomorrow morning. THANKS FOR YOUR COOPERATION!
Road Work to Start Week of June 26, 2023
June 27 & 28, 2023 - Gedney Street, Lydecker Street, Upper Main Street and Pine Street are scheduled for road milling. The milling process is scheduled to last two days. Roads will be reopened immediately following - please drive carefully over milled roads. The construction is scheduled to start on Gedney St, then Lydecker St and possibly Upper Main Street on June 27, 2023. Work will continue on June 28 on Upper Main Street (if necessary) and Pine Street.
June 30 & July 3, 2023 - Roads will be paved in the order listed above. Paving is expected to last two days. Please follow road closures and detours in the village. After the paving, roads will remain blocked for several hours until the pavement is drivable.
ALL CARS OFF THE ROADS & OUT OF DRIVEWAYS BY 7AM ON MILLING & PAVING DAYS.
WHERE TO PARK ?? CLICK HERE!!
Gedney Street and Lydecker Street residents may use the marina lot, at no charge, on paving day. Any cars on the road after 7am will be towed.
Pine Street & Upper Main Street residents may find parking, courtesy of the Nyack School District, at the Nyack Middle School and side streets.
EXACT PAVING DATES WILL BE POSTED AS SOON AS AVAILABLE. ROAD CONSTRUCTION IS WEATHER DEPENDENT AND SUBJECT TO CHANGE.
Paving for 2023 is scheduled on the following village streets:
Tilcon NY is scheduled for paving over the summer months, as soon as we have a schedule, notification will be made. Indus Inc. will also be working in the village in the coming months to crack seal on the following roads: North Midland Ave, Jackson Ave, Sixth Ave, High Ave (Rte 9w to Midland Ave), Liberty St, Tallman Ave, Grand Ave, Fifth Ave (Midland Ave to Francis Ave), Second Ave, Third Ave.
Nyack DPW will focus on some areas with milling and patching. There are a number of streets that are scheduled for water main replacement in 2023 and 2024 and a complete repaving will follow that work - those streets include: Marion Street, Jefferson Street, First Avenue (Broadway to N. Franklin St), Central Ave (5th to 6th), Francis Avenue, Church Street, Cedar Street, Park Street, Bridge Street.
Road Paving 2011 - 2020 a 10 year road map!