The Water Department, in collaboration with its engineering consultant H2M and independent contractors, is undertaking a multi-million-dollar upgrade to the water lines and valves in Central Nyack, West Nyack, and select streets in the Village of Nyack. This project involves the replacement of water mains and lateral lines, which will require excavations in the roadways.
Once excavation work is completed, the trenches will be filled in. The Water Department is working closely with Clarkstown Highway Department, to ensure that the re-paving of trenches in Central Nyack and West Nyack meets the standards outlined in town-issued permits. Streets in the Village of Nyack will also be repaved as part of the Village's annual paving program.Â
Phase A of the Water Main Replacement Project was successfully completed between 2020 and 2022. Phase B construction has started November 2024.Â
Water Main Project in Nyack -Â UPDATED SCHEDULE!!
Project Details:Â First Avenue
Project Details: Francis Avenue (5th Ave to 6th Ave)
During the course of this project, residents may experience construction-related noise and temporary disruptions in water service. Please note the following planned water outages:
We will make every effort to minimize any inconvenience and ensure that the work is completed as efficiently and safely as possible.
We appreciate your patience and understanding as we work to improve the water infrastructure in Nyack. Thank you for your cooperation.
Â
Notice: Water Main Installation on Central Ave (December 13-18, 2024)
Update: Work scheduled to begin on Tuesday, December 10th has been delayed until Friday, December 13th, 2024, and will continue into the week of December 16th. Fletcher Creamer, the contractor hired by the Nyack Water Department, will be installing a new water main on Central Avenue, between 5th and 6th Avenues.
What to Expect:
We appreciate your patience and cooperation as we work to upgrade our water infrastructure. If you have any questions, please contact the Nyack Water Department at 845-358-3734.
Thank you for your understanding!
11/20/24: Phase B Construction
Phase B of the Water Main Replacement Project is now under construction in West Nyack and the Village of Nyack, starting with Central Ave and Francis Ave. Work will then progress to Jefferson Ave and Marion St in the coming weeks. This phase focuses on replacing the oldest, most failure-prone water lines in the Village.
Project Details:
Minimizing Disruption:
Project Oversight:
We have partnered with the highly reputable contractor, Fletcher Creamer & Sons, overseen by H2M Engineering. An H2M inspector will be on-site at all times, overseeing the work flow and ensuring that it meets all quality standards. The Nyack Water Department staff collaborates closely with the team, providing essential mark-outs of existing water infrastructure and supporting the project in various capacities.
Restoration:
The following streets are scheduled for water main work during Phase B of this project, with construction taking place from Fall 2024 to Summer 2025:
The Water Department is upgrading its treatment plant to effectively remove PFOS/PFAS contaminants in compliance with state and federal regulations. Designed by H2M Engineers, this important project is nearing completion and is expected to go out to bid in January 2025. The total project cost is approximately $6.7 million, with a significant portion funded through grants and New York State financing.Â
The design for the PFOS/PFAS treatment process is largely complete, pending approval from the Department of Health. The project is on track to be ready for competitive bidding in January 2025, with construction expected to begin shortly thereafter.
For more information on PFOS/PFAS contamination, please visit the Water Department home page, or refer to the annual water quality report and PFAS/PFOA reports.Â
Â