Nyack Water Department: Water Main Project Update - March 26, 2025

Nyack Water Department: Water Main Project Update - March 26, 2025

The Nyack Water Department's Water Main Project on Fifth Avenue will continue for approximately four more weeks, including the area between Midland Avenue and North Broadway.


Completed Work:

New water mains have been installed on First Avenue, Marion Street, Jefferson Street, Central Avenue, and Frances Avenue.

Ongoing Work:

Installation of new service lines between the water mains and homes is in progress.

Marion Street: Targeted for early April.

Jefferson Street: Expected in mid- to late-April.


Parking and Access: Fletcher Creamer, our contractor, will continue to post parking restriction signage as needed and coordinate with residents to ensure driveway access.

We appreciate your patience and cooperation as we complete this vital infrastructure project.

More: Home Page News